Terminal A-Plus, Frankfurt am Main
Frankfurt am Main, Germany
·
Airport
Project

800 meters, four years, delivered on schedule.

Terminal A-Plus: an 800-meter western extension of Frankfurt Airport's Terminal 1, opened October 2012, adding capacity for 65 million passengers per year including 4 Airbus A380 stands.

app.prob.is/airports/terminal-a-plus

Terminal A-Plus, Frankfurt · Calculate view

PROBIS Calculate · Estimated Figures
  • 800-meter pierextension
  • 65 million passengersadded per year
PackageBudgetVarianceStatus
Pier Structure€260M−0.8%On budget
Gate Systems€80M+7.5%Review
MEP & Systems€70M0.0%On budget
Apron & Landside€40M0.0%On budget

These are indicative figures only, based on published project information. They are not actual PROBIS project data.

Overview
Invoices
Exam
Approval
Costs
Report
Pier extension
800m
Passengers added per year
65M
Terminal A-Plus, Frankfurt am Main
Incoming invoices
New
RE-2026-0418
Rohbau Nord GmbH · PDF
Contract
300.01 Structural Work
Large amount
184,200.00 €
Service period
09/2026
✓ Data detected
→ Assigned to a contract
Cash-out plan
Plan · Actual · Outflow
2017
2019
2021
2023
2026
Costs
3 of 4 within budget
Package
Budget
Forecast
Status
Pier Structure
€260M
€258M
On budget
Gate Systems
€80M
€86M
Review
MEP & Systems
€70M
€70M
On budget
Apron & Landside
€40M
€40M
On budget

Illustrative only — figures are fictional and do not represent the program's actual line-item data.

Fraport AG
Client
Calculate
Contract
Control
The project

The project, by the numbers.

Terminal A-Plus: an 800-meter western extension of Frankfurt Airport's Terminal 1, opened October 2012, adding capacity for 65 million passengers per year including 4 Airbus A380 stands.

After approximately four years of construction, Frankfurt Airport opened Pier A-Plus—the 800-meter-long western extension of Terminal 1—in October 2012, as scheduled. With this expansion, designed by gmp, Germany’s largest air traffic hub can now handle approximately 65 million passengers per year. It features seven boarding gates for long-haul aircraft, four of which are designed for the Airbus A380.

Location
Frankfurt am Main, Germany
Timeframe
2008
Asset class
Airport
Scope
Cost management with PROBIS Calculate, Contract, and Control.
Client
Fraport AG
  • 800-meter pier extension
  • 65 million passengers added per year
On the platform

The modules behind this project.

The PROBIS modules used in this project, shown on sample screens with demo data.

Calculate
Cost calculation based on quantity surveying, starting from the earliest planning stage.
Contract
Contracts and commitments are tracked starting from the pre-construction phase, not from the first invoice.
Control
Forecast and actual figures are reconciled continuously, line item by line item.
app.prob.is/projects/
Terminal A Plus, Frankfurt am Main

Terminal A-Plus, Frankfurt · Calculate view

PROBIS Calculate · Estimated Figures
  • 800-meter pierextension
  • 65 million passengersadded per year
PackageBudgetVarianceStatus
Pier Structure€260M−0.8%On budget
Gate Systems€80M+7.5%Review
MEP & Systems€70M0.0%On budget
Apron & Landside€40M0.0%On budget

These are indicative figures only, based on published project information. They are not actual PROBIS project data.

app.prop.is/projects/northwind-yards

Northwind Yards · Expected completion date

PROBIS Control · Demo Data
  • $104.5M Budget
  • $101.3M Committed
  • $66.9 million invoiced
  • +1.2% Forecastvariance
PackageBudgetForecastStatus
Shell & Core$38.2M$38.0MOn budget
Facade$14.6M$15.3MReview
MEP$27.9M$28.4MReview
Fit-out$16.4M$16.4MOn budget

Projected total upon completion: $105.8 million. Sample screen with fictional demo data.

Calculate
Contract
Control
The client
Fraport AG

Fraport AG operates 31 airports across four continents. Since 2017, PROBIS has served as the central interface for Fraport's project data, starting with Frankfurt, Germany's largest air traffic hub.

View client