Airport Expansion: South Terminal 3
Frankfurt am Main, Germany
·
Airport
Project

45 projects. A financial perspective.

Frankfurt Airport Terminal 3.

Terminal 3 at Frankfurt Airport opened on April 22, 2026—on schedule and within budget, after nine years of construction, which were monitored by PROBIS from the initial quantity and cost estimates through to completion.

app.prob.is/airports/program-overview
Overview
Invoices
Exam
Approval
Costs
Report
Budget
€104.5M
Commissioned
€101.3M
Billed
€66.9M
Forecast Variance
+1.2%
Airport Expansion: South Terminal 3
Incoming Invoices
New
RE-2026-0418
Rohbau Nord GmbH · PDF
Contract
300.01 Structural Work
Gross Amount
184,200.00 €
Service Period
09/2026
✓ Data detected
→ Assigned to a contract
Cash Flow Statement
Plan · Actual · Outflow
M1
M6
M12
M18
M24
Costs
2 out of 4 within budget
PackageBudgetProgramStatus
Structural Work & Core€38.2M€38.0MWithin budget
Facade€14.6M€15.3MAudit
TGA€27.9M€28.4MAudit
Expansion€16.4M€16.4MWithin budget
Projected cost upon completion: €105.8 million. Illustrative screenshot with fictitious demo data.
Cost per square meter
€3,480
Benchmark
€3,410
Cost Items
312
Comparative Projects
18
Airport Expansion: South Terminal 3
Estimate vs. Median
Structural Work
Facade
TGA
Expansion
Estimate
Median
Cost per square meter vs. comparable projects
18 projects
Low
Median
High
Cost Groups
3 out of 4 within the framework
Cost GroupEstimateMedianStatus
Structural Work & Core€38.2M€37.6MAs part of
Facade€14.6M€13.4MAbove
TGA€27.9M€27.1MAs part of
Expansion€16.4M€16.9MAs part of
Estimated value: €104.5 million, benchmarked against 18 comparable projects. Illustrative screenshot with fictitious demo data.
Projects
4
Total Budget
€412M
Early Warnings
2
Funding Coverage
96%
Airport Expansion: South Terminal 3
Early Warning
New
EW-2026-007
Riverside Campus · TGA Package
Forecast Variance
+7.1%
Responsible
Project Management
Decision Due
November 2026
✓ Automatically selected
→ Assigned to the person in charge
Budget per Project
Budget · Forecast
Northwind
Harbor
Elm St
Riverside
Portfolio
2 Early Warnings
ProjectBudgetVarianceStatus
Northwind Yards€104.5M+1.2%Within budget
Harbor Point€138M+3.8%Audit
Elm Street Lofts€61M−0.4%Within Budget
Riverside Campus€108M+7.1%Early Warning
Two early warnings triggered, each with a designated person in charge and a decision deadline. Illustrative screenshot with fictitious demo data.
Bids Received
5
Budget line item
€14.6M
Lowest vs. Budget
−3.4%
Change Orders
6
Airport Expansion: South Terminal 3
Change Orders
2 new
CO-2026-016
Facade Package · Meridian Facades
Reason
Change to the Glazing Specifications
Amount
+124,000.00 €
Recorded so far
6 · 420,000 €
✓ Within the budget line item
→ Awaiting approval
Bids vs. Budget Line Item
€14.6M Budget
Commandment 1
Commandment 3
Commandment 5
Award of the Facade Contract Package
Awarded for €14.3M
BidderBidvs. BudgetStatus
Alder Facades€14.1M−3.4%Non-compliant
Meridian Facades€14.3M−2.1%Awarded
Kestrel Envelope€14.8M+1.4%Shortlist
Norland Glass€15.9M+8.9%Rejected
Contracts awarded for €14.3 million against a budget allocation of €14.6 million. Illustrative screenshot with fictitious sample data.
Fraport AG
Customer
Calculate
Contract
Control
The Project

The Project in Numbers.

In the southern part of Frankfurt Airport, the new Terminal 3 is being built on the site of the former U.S. military base; starting in 2023, it will be able to handle up to 21 million passengers per year.

Terminal 3 is being built on the site of the former U.S. military base in the southern part of Frankfurt Airport. Once completed in 2023, the new terminal will be able to handle up to 21 million passengers per year. At full capacity, Terminal 3 is designed to handle approximately 25 million passengers.

Location
Frankfurt am Main, Germany
Time period
2014
–
2023
Asset Class
Airport
Scope
Software Services and Consulting for Fraport with PROBIS.
Customer
Fraport AG
  • 2017 PROBIS in use since
  • 45 subprojects
  • Program volume of 5+ billion euros
  • ~100 registered users today
On the platform

The modules behind this project.

The PROBIS modules used in this project, displayed on illustrative screens with sample data.

Calculate
Cost calculation based on quantity surveying, starting from the earliest planning stage.
Contract
Contracts and commitments are tracked starting from the pre-construction phase, not from the first invoice.
Control
Forecast and actual figures are reconciled continuously, line item by line item.
app.prob.is/projects/
airport-expansion-south-terminal-3-frankfurt-on-the-main
Overview
Invoices
Exam
Approval
Costs
Report
Budget
€104.5M
Commissioned
€101.3M
Billed
€66.9M
Forecast Variance
+1.2%
Airport Expansion: South Terminal 3
Incoming Invoices
New
RE-2026-0418
Rohbau Nord GmbH · PDF
Contract
300.01 Structural Work
Gross Amount
184,200.00 €
Service Period
09/2026
✓ Data detected
→ Assigned to a contract
Cash Flow Statement
Plan · Actual · Outflow
M1
M6
M12
M18
M24
Costs
2 out of 4 within budget
PackageBudgetProgramStatus
Structural Work & Core€38.2M€38.0MWithin budget
Facade€14.6M€15.3MAudit
TGA€27.9M€28.4MAudit
Expansion€16.4M€16.4MWithin budget
Projected cost upon completion: €105.8 million. Illustrative screenshot with fictitious demo data.
Cost per square meter
€3,480
Benchmark
€3,410
Cost Items
312
Comparative Projects
18
Airport Expansion: South Terminal 3
Estimate vs. Median
Structural Work
Facade
TGA
Expansion
Estimate
Median
Cost per square meter vs. comparable projects
18 projects
Low
Median
High
Cost Groups
3 out of 4 within the framework
Cost GroupEstimateMedianStatus
Structural Work & Core€38.2M€37.6MAs part of
Facade€14.6M€13.4MAbove
TGA€27.9M€27.1MAs part of
Expansion€16.4M€16.9MAs part of
Estimated value: €104.5 million, benchmarked against 18 comparable projects. Illustrative screenshot with fictitious demo data.
Bids Received
5
Budget line item
€14.6M
Lowest vs. Budget
−3.4%
Change Orders
6
Airport Expansion: South Terminal 3
Change Orders
2 new
CO-2026-016
Facade Package · Meridian Facades
Reason
Change to the Glazing Specifications
Amount
+124,000.00 €
Recorded so far
6 · 420,000 €
✓ Within the budget line item
→ Awaiting approval
Bids vs. Budget Line Item
€14.6M Budget
Commandment 1
Commandment 3
Commandment 5
Award of the Facade Contract Package
Awarded for €14.3M
BidderBidvs. BudgetStatus
Alder Facades€14.1M−3.4%Non-compliant
Meridian Facades€14.3M−2.1%Awarded
Kestrel Envelope€14.8M+1.4%Shortlist
Norland Glass€15.9M+8.9%Rejected
Contracts awarded for €14.3 million against a budget allocation of €14.6 million. Illustrative screenshot with fictitious sample data.
Projects
4
Total Budget
€412M
Early Warnings
2
Funding Coverage
96%
Airport Expansion: South Terminal 3
Early Warning
New
EW-2026-007
Riverside Campus · TGA Package
Forecast Variance
+7.1%
Responsible
Project Management
Decision Due
November 2026
✓ Automatically selected
→ Assigned to the person in charge
Budget per Project
Budget · Forecast
Northwind
Harbor
Elm St
Riverside
Portfolio
2 Early Warnings
ProjectBudgetVarianceStatus
Northwind Yards€104.5M+1.2%Within budget
Harbor Point€138M+3.8%Audit
Elm Street Lofts€61M−0.4%Within Budget
Riverside Campus€108M+7.1%Early Warning
Two early warnings triggered, each with a designated person in charge and a decision deadline. Illustrative screenshot with fictitious demo data.
Calculate
Contract
Control
The Customer
Fraport AG

Fraport AG operates 31 airports on four continents. Since 2017, PROBIS has served as the central interface for Fraport’s project data, starting in Frankfurt, Germany’s largest air traffic hub.

View Customer

Managing an airport construction project using spreadsheets?

Would you like to have the same level of control on your next project?