Lima's airport expansion, according to one leading cost model.

Lima Airport Partners is the Fraport-controlled concession operator of Jorge Chávez International Airport in Lima, Peru, holding the operating concession through 2041.

app.prob.is/airports/lima
Jorge Chavez Program Overview
New Terminal, Jorge Chávez International Airport, Lima
3 of 4 within budget
Package
Budget
Forecast
Status
New Terminal
$900M
$895M
On budget
Second Runway
$400M
$410M
Review
Control Tower
$150M
$148M
On budget
Landside Access
$50M
$50M
On budget

Illustrative only — figures are fictional and do not represent the program's actual line-item data.

New Terminal, Jorge Chávez International Airport, Lima
New Terminal, Jorge Chávez International Airport, Lima
Lima, Peru
Calculate
Control
Manage
At a Glance
Industry
Airports
Client type
2025
New terminal opened within a ~USD 2B expansion program
270,000 m²
Size of the new terminal
40M
Passengers per year, design capacity
How they work with PROBIS

Cost data produced and validated by PROBIS professionals.

PROBIS holds budget, forecast, and cash flow for the expansion program in one leading cost model, with cost estimation and benchmarks built on Calculate. The engagement combines the platform with PROBIS quantity surveying capacity, so cost data is produced and validated by PROBIS professionals rather than collected from the client. Integration runs through an SAP ERP interface and an Awaro CDE interface.

Lima Airport Partners
On the platform

Four modules, one leading cost model.

The PROBIS modules that power client programs, shown on sample screens with demo data.

Calculate
Estimates and benchmarks establish a defensible baseline.
Contract
Awards, change orders, and invoices are verified against the budget.
Control
Forecasts and cash flow are tracked against the plan, with risks identified early on.
Manage
Reporting for management, investors, and lenders based on a single data set.
app.prob.is/calculate
Lima Airport Partners
Estimate basis · Project key figures
Calculate

New Terminal, Jorge Chávez, Lima · Calculate view

PROBIS Calculate · Estimated Figures
  • 3Concurrentpackages
  • $1.5–2B Totalinvestment
PackageBudgetVarianceStatus
New Terminal$900M−0.6%On budget
Second Runway$400M+2.5%Review
Control Tower$150M−1.3%On budget
Landside Access$50M0.0%On budget

These are indicative figures only, based on published project information. They are not actual PROBIS project data.

Illustrative view. Key figures from the client's project profiles.
app.prop.is/projects/northwind-yards

Northwind Yards · Cost Estimate vs. Benchmark

PROBIS Calculate · Demo Data
  • $3,480 persquare meter of gross floor area
  • $3,410 Benchmarkmedian
  • 312 CostItems
  • 18Comparables
Cost GroupEstimateMedianStatus
Shell & Core$38.2M$37.6MWithin range
Facade$14.6M$13.4MAbove the median
MEP$27.9M$27.1MWithin range
Fit-out$16.4 million$16.9MWithin range

Estimated at $104.5 million, based on a comparison with 18 similar projects. Illustrative screen with fictional demo data.

app.prop.is/projects/northwind-yards
Estimated cost: Northwind Yards
Updated 4 minutes ago
On budget
$104.5M
Total budget
+1.2%
Forecast variance
$101.3M
Committed
64%
Progress
Illustrative screenshot with fictional demo data.
Control
Calculate
Contract
Projects

Projects on PROBIS.

New Terminal, Jorge Chávez International Airport, Lima
New Terminal, Jorge Chávez International Airport, Lima
Lima Airport Partners · Three Packages, One Platform

Three concurrent projects—a new terminal, a second runway, and a new control tower—were consolidated into a single view, with results clearly rolled up into the parent company Fraport’s financial statements.