<span>Amazon Headquarters, East Side Tower</span><br>
Berlin, Germany
·
Mix
Project

Five financing banks. A shared perspective on construction risk.

The East Side Tower in Berlin—which is financing Amazon’s European headquarters—is being monitored on PROBIS Banks on behalf of a consortium of five banks led by Deutsche Pfandbriefbank, replacing the fragmented spreadsheet workflows that are common in large real estate financing transactions.

app.prob.is/bank/east-side-tower
Overview
Invoices
Exam
Approval
Costs
Report
Budget
€104.5M
Commissioned
€101.3M
Billed
€66.9M
Forecast Variance
+1.2%
Amazon Headquarters, East Side Tower
Incoming Invoices
New
RE-2026-0418
Rohbau Nord GmbH · PDF
Contract
300.01 Structural Work
Gross Amount
184,200.00 €
Service Period
09/2026
✓ Data detected
→ Assigned to a contract
Cash Flow Statement
Plan · Actual · Outflow
M1
M6
M12
M18
M24
Costs
2 out of 4 within budget
PackageBudgetProgramStatus
Structural Work & Core€38.2M€38.0MWithin budget
Facade€14.6M€15.3MAudit
TGA€27.9M€28.4MAudit
Expansion€16.4M€16.4MWithin budget
Projected cost upon completion: €105.8 million. Illustrative screenshot with fictitious demo data.
Cost per square meter
€3,480
Benchmark
€3,410
Cost Items
312
Comparative Projects
18
Amazon Headquarters, East Side Tower
Estimate vs. Median
Structural Work
Facade
TGA
Expansion
Estimate
Median
Cost per square meter vs. comparable projects
18 projects
Low
Median
High
Cost Groups
3 out of 4 within the framework
Cost GroupEstimateMedianStatus
Structural Work & Core€38.2M€37.6MAs part of
Facade€14.6M€13.4MAbove
TGA€27.9M€27.1MAs part of
Expansion€16.4M€16.9MAs part of
Estimated value: €104.5 million, benchmarked against 18 comparable projects. Illustrative screenshot with fictitious demo data.
Projects
4
Total Budget
€412M
Early Warnings
2
Funding Coverage
96%
Amazon Headquarters, East Side Tower
Early Warning
New
EW-2026-007
Riverside Campus · TGA Package
Forecast Variance
+7.1%
Responsible
Project Management
Decision Due
November 2026
✓ Automatically selected
→ Assigned to the person in charge
Budget per Project
Budget · Forecast
Northwind
Harbor
Elm St
Riverside
Portfolio
2 Early Warnings
ProjectBudgetVarianceStatus
Northwind Yards€104.5M+1.2%Within budget
Harbor Point€138M+3.8%Audit
Elm Street Lofts€61M−0.4%Within Budget
Riverside Campus€108M+7.1%Early Warning
Two early warnings triggered, each with a designated person in charge and a decision deadline. Illustrative screenshot with fictitious demo data.
Bids Received
5
Budget line item
€14.6M
Lowest vs. Budget
−3.4%
Change Orders
6
Amazon Headquarters, East Side Tower
Change Orders
2 new
CO-2026-016
Facade Package · Meridian Facades
Reason
Change to the Glazing Specifications
Amount
+124,000.00 €
Recorded so far
6 · 420,000 €
✓ Within the budget line item
→ Awaiting approval
Bids vs. Budget Line Item
€14.6M Budget
Commandment 1
Commandment 3
Commandment 5
Award of the Facade Contract Package
Awarded for €14.3M
BidderBidvs. BudgetStatus
Alder Facades€14.1M−3.4%Non-compliant
Meridian Facades€14.3M−2.1%Awarded
Kestrel Envelope€14.8M+1.4%Shortlist
Norland Glass€15.9M+8.9%Rejected
Contracts awarded for €14.3 million against a budget allocation of €14.6 million. Illustrative screenshot with fictitious sample data.
Edge Technologies
Customer
Control
Calculate
Contract
The Project

The Project in Numbers.

A 142-meter-tall, 38-story skyscraper in Berlin, financed by Amazon's European headquarters, is being monitored on PROBIS by banks acting on behalf of a consortium of five banks.

The East Side Tower is a 142-meter-tall, 38-story high-rise in Berlin-Friedrichshain, designed by BIG – Bjarke Ingels Group, and serves as Amazon’s European headquarters. Construction monitoring is being carried out using PROBIS Banks on behalf of a financing consortium consisting of Deutsche Pfandbriefbank AG, Commerzbank AG, HELABA – Landesbank Hessen-Thüringen, Berlin Hyp AG, and Berliner Sparkasse.

Real estate financing on this scale is inherently complex—a single project can involve 20 to 100 parties and generate up to 1,200 files, creating an ideal breeding ground for inefficiencies and cost overruns. The PROBIS Project-Clock module provides financing banks with real-time risk detection, centralized fund tracking, and AI-generated reports, replacing disconnected spreadsheet workflows with a single, reliable source of data.

Location
Berlin, Germany
Time period
Asset Class
Mix
Scope
Construction monitoring using PROBIS Banks for a financing consortium consisting of Deutsche Pfandbriefbank AG, Commerzbank AG, HELABA – Landesbank Hessen-Thüringen, Berlin Hyp AG, and Berliner Sparkasse. Project-Clock from PROBIS Finance for the financing banks, featuring cloud-based monitoring of fund usage and all parameters displayed in the Finance Dashboard.
  • 142 m height of the tower
  • 5 banks in the consortium
  • 38 floors
  • 80,500 m² gross floor area
  • 65,000 m² of leasable office and restaurant space
On the platform

The modules behind this project.

The PROBIS modules used in this project, displayed on illustrative screens with sample data.

Control
Forecast and actual figures are reconciled continuously, line item by line item.
Calculate
Cost calculation based on quantity surveying, starting from the earliest planning stage.
Contract
Contracts and commitments are tracked starting from the pre-construction phase, not from the first invoice.
app.prob.is/projects/
east-side-tower-berlin
Overview
Invoices
Exam
Approval
Costs
Report
Budget
€104.5M
Commissioned
€101.3M
Billed
€66.9M
Forecast Variance
+1.2%
Amazon Headquarters, East Side Tower
Incoming Invoices
New
RE-2026-0418
Rohbau Nord GmbH · PDF
Contract
300.01 Structural Work
Gross Amount
184,200.00 €
Service Period
09/2026
✓ Data detected
→ Assigned to a contract
Cash Flow Statement
Plan · Actual · Outflow
M1
M6
M12
M18
M24
Costs
2 out of 4 within budget
PackageBudgetProgramStatus
Structural Work & Core€38.2M€38.0MWithin budget
Facade€14.6M€15.3MAudit
TGA€27.9M€28.4MAudit
Expansion€16.4M€16.4MWithin budget
Projected cost upon completion: €105.8 million. Illustrative screenshot with fictitious demo data.
Cost per square meter
€3,480
Benchmark
€3,410
Cost Items
312
Comparative Projects
18
Amazon Headquarters, East Side Tower
Estimate vs. Median
Structural Work
Facade
TGA
Expansion
Estimate
Median
Cost per square meter vs. comparable projects
18 projects
Low
Median
High
Cost Groups
3 out of 4 within the framework
Cost GroupEstimateMedianStatus
Structural Work & Core€38.2M€37.6MAs part of
Facade€14.6M€13.4MAbove
TGA€27.9M€27.1MAs part of
Expansion€16.4M€16.9MAs part of
Estimated value: €104.5 million, benchmarked against 18 comparable projects. Illustrative screenshot with fictitious demo data.
Bids Received
5
Budget line item
€14.6M
Lowest vs. Budget
−3.4%
Change Orders
6
Amazon Headquarters, East Side Tower
Change Orders
2 new
CO-2026-016
Facade Package · Meridian Facades
Reason
Change to the Glazing Specifications
Amount
+124,000.00 €
Recorded so far
6 · 420,000 €
✓ Within the budget line item
→ Awaiting approval
Bids vs. Budget Line Item
€14.6M Budget
Commandment 1
Commandment 3
Commandment 5
Award of the Facade Contract Package
Awarded for €14.3M
BidderBidvs. BudgetStatus
Alder Facades€14.1M−3.4%Non-compliant
Meridian Facades€14.3M−2.1%Awarded
Kestrel Envelope€14.8M+1.4%Shortlist
Norland Glass€15.9M+8.9%Rejected
Contracts awarded for €14.3 million against a budget allocation of €14.6 million. Illustrative screenshot with fictitious sample data.
Projects
4
Total Budget
€412M
Early Warnings
2
Funding Coverage
96%
Amazon Headquarters, East Side Tower
Early Warning
New
EW-2026-007
Riverside Campus · TGA Package
Forecast Variance
+7.1%
Responsible
Project Management
Decision Due
November 2026
✓ Automatically selected
→ Assigned to the person in charge
Budget per Project
Budget · Forecast
Northwind
Harbor
Elm St
Riverside
Portfolio
2 Early Warnings
ProjectBudgetVarianceStatus
Northwind Yards€104.5M+1.2%Within budget
Harbor Point€138M+3.8%Audit
Elm Street Lofts€61M−0.4%Within Budget
Riverside Campus€108M+7.1%Early Warning
Two early warnings triggered, each with a designated person in charge and a decision deadline. Illustrative screenshot with fictitious demo data.
Control
Calculate
Contract
The Customer
Edge Technologies

EDGE is a global company that specializes in the development and digitization of smart buildings and intelligent infrastructure solutions.

View Customer

Check fund allocation based on a live position instead of a PDF?

Would you like to have the same level of control on your next project?